A total of N700,538,741691.30 budgeted for the Ministry of Niger Delta Affairs between 2009 and 2015 with 60 per cent disbursement, has yielded only eight per cent impact in the region, a development that may have continued to ignite the seemingly unending violent agitations by youths in the area.
A Technical Audit Committee set up by
the Minister of Niger Delta Affairs, Pastor Usani Uguru Usani, which
turned in its report yesterday, said the total cost of projects within
the period was N700,538,741,691.30, excluding services (security, rent
and facility management).
According to the committee headed by
Yerima Bulama, a cumulative sum of N446,421,385,864.41 was certified for
payment but N423,172,256,347.84 was paid, leaving an outstanding of
N32,111,887,779.32.
In other words, between 2009 and 2015, about 60 per cent of 425 projects awarded were paid for, but approximately 40 per cent of work was practically achieved, the report said
In other words, between 2009 and 2015, about 60 per cent of 425 projects awarded were paid for, but approximately 40 per cent of work was practically achieved, the report said
The Bulama committee said there was
evidence of repetition of programmes and conflict of projects in the
region by the Niger Delta Affairs Ministry, Niger Delta Development
Commission (NDDC), Niger Delta Amnesty Programme, state and local
governments.
It reported a violation of contract
award process right from the cycle of procurement planning to contract
award as inconsistencies with the provisions of vital aspects of the
Procurement Act were rife.
It also found out cases of
indiscriminate award of contract by initiating and benefiting
departments without the leading and guiding role of the procurement
department. Contract awards also never took cognisance of availability
of funds and annual appropriation provisions, the report said, adding
that the structure and content of some contract agreements were loose
for checks and balances, and hardly protected the interest of the
ministry in case of disputes.
On delivery and capacity, the Bulama
committee noted that the imminent picture of abandoned and uncompleted
projects was as disturbing as the retinue of projects that extremely
exceeded the dates of completion.
“This manifestly emanated from
inconsistency in government annual budgetary provision and lack of
capacity to deliver especially where funds released do not correspond
with performance. Most contracts were awarded with specific dates of
completion but were not captured in subsequent appropriations.
“This further exacerbated contractors’ poor performance and inability to achieve project objectives.
Consequently, no capital project was completed within the stipulated time frame,” the report said.
Consequently, no capital project was completed within the stipulated time frame,” the report said.
It added that it was obviously revealing
that the ministry and its consultants alike had neither well-structured
nor coordinated monitoring nor evaluation (M&E) mechanisms, which
ought to have been pre-scheduled and followed tenaciously.
“In some cases, Engineers
Representatives (ER) and the consultants as well as the Planning,
Research and Statistics Department (PRSD) have broad discrepancies in
performance, certification, dimension and quality of delivery. As a
matter of fact, the ministry’s state coordinators had little or no
knowledge of projects scopes and locations.
source: thisdaylive
No comments:
Post a Comment